7mm aluminium alloy 3105 h46 temper pvf2 colour finish.
Roof sheet installation method statement.
Safety method statement prepared by humphrey and gray ltd.
The procedure shall be read in conjunction with contract specification wherever applicable.
Length of nail shall suit the application and roof sheet manufacturer s recommendations.
Before laying the screed cement slurry shall be brushed across the surface.
All locations to be marked as per approved drawing.
The base plate level and the center line of the truss column shall be marked based on reference datum and coordinate points given by main contractor surveyor.
A completed sample template has been included in appendix 1 and a blank template in appendix 2.
Roof installation method statement a basic guide to preparation introduction this guidance note gives practical information about creating a method statement.
The roofing and cladding shall consist of outer and inner profiled steel sheets with an insulation blanket between them.
Before starting the roof steel truss installation necessary scaffolding or working platform shall be provided with green tag to reach and work at the height safely.
Note this method statement has been developed using the site specific risk assessment the designer s residual risk register the trussed rafter association s product data sheets and health and safety in roof work hsg33.
Implements and maintains safe working environment by adhering to correct work practices and procedures.
Coordinate all installation delivery and safety activities at site.
If you wish to use the template in appendix 2 to construct your own documents.
The screed shall be finished smooth to receive further finish as specified.
Ensure all items to be installed on the roof which require penetrations through the roof membrane are placed prior to the application of the membrane.
This swms covers high risk construction work hrcw controls related to.
Roofing screws for corrugated sheets shall be galvanised and are to conform to bs 1494.
1965 and be complete with plastic washers.
The method statement was prepared by.
This roofing sheeting safe work method statement swms covers hazards and controls associated with the installation of a corrugated iron roof use and subsequent dismantling of roof edge protection systems.
This fabrication method statement covers the detailed procedure for fabrication and installation of any kind of steel structure decking slabs.